September 8, 2022

Community Update
by John A. Corella, PE, Director of Engineering & Public Works

ramon-rd-east-paving-026

Update on the City’s Paving Reconstruction Projects

Last month, we started construction on four paving projects in the City that represents close to $2.0 million of additional expenditures on our roadways. Work is progressing quickly, and the following is an update on the progress of these projects.

Century Park Neighborhood Street Project
This Project started a few weeks back with concrete ADA corner ramp replacements, and curb and gutter replacements. These have been completed. Now, we are midway through the paving portion of the Project. This paving work will halt for a few days in order for the forecasted rain and thunderstorm to pass the area. Once the rain storm passes, paving operations will resume in the area. Once the paving operations are completed, the stop bars, crosswalks, and minimal striping in the area will be applied. All the work in this area should be completed within two weeks. A map of the streets where work is continuing is shown below.
cp1
The Century Park Rehabilitation Project Streets

Sarah Street Pavement Rehabilitation
The paving work for Sarah Street Project was started this past Wednesday. The concrete work, e.g. driveways, curbs and gutter were completed at the beginning of last week. Remarkably, and motivated by the upcoming weather conditions, the contractor completed the paving portion of the work in one day! That was over 1,400 tons of asphalt placed in this light industrial/commercial area with 70 truck loads of hot asphalt delivered. The traffic loop replacement at the Crossley Road/Ramon Road intersection will be completed early tomorrow morning (4:00 am) and the minimal striping and stop bars will be applied early next week, weather permitting. The map below shows the location of the work.
ss2
The Sarah Street Project

Avenida Los Ninos Surface Widening and Via De Anza Street Rehabilitation Projects
These Projects involve the widening of half the streets either to provide an added vehicle lane and/or add improvements such as curb, gutter, and sidewalk.

The Avenida Los Ninos Project
The Avenida Los Ninos Project will be starting tomorrow. The contractor will proceed with grinding operations tomorrow and will continue until the forecasted rain makes it too difficult to proceed. Depending on how the contractor completes completed tomorrow, the contractor may have to continue the grinding operations on Monday. Once the contractor completes the grinding operations next week, the contractor will immediately proceed with the paving portion of the Project, widening the street by 17 feet on the east side from north of McCallum Way to 30th Avenue. This Project should be completed by the end of next week. The Project location is shown below.
aln3
The Avenida Los Ninos Project

The Via De Anza Rehabilitation Project Phase 1
This very involved Project, just north of Dinah Shore Drive on Via De Anza, is in the final stages of completion. This Project required the removal of a significant amount of landscaping, hardscaping, walls and accessories that had been placed in the right of way prior to the City’s incorporation and the following years. The completed improvements included the installation of asphalt paving on the west half of the street with full half street width paving, driveways, curb and gutter and sidewalk. There are few more improvements that the contractor has left to complete off the roadway and within the right of way behind the new sidewalk. Once the materials necessary to complete this final work are delivered (projected at a month out), the contractor will complete the work and the City can proceed to close out the Project. A map of the improvement area is shown below.
vda4
The Via De Anza Project

Note: The City Engineering Staff is already working on the Project design for the portions that involve the east side of the street, Via De Anza Phase 2, which will be completed next year.

Summary
I have commented on the upcoming thunderstorm that is forecasted for tomorrow and over the upcoming weekend. This means that the streets will be wet and there may be localized flooding during and after the rain. The current areas where flooding may close and reduce the roadway widths are as follows:
  • Varner Road just north of Edom Hill Road
  • Date Palm Drive and Los Gatos
  • Vista Chino at the Whitewater River Crossing
Please note that we are working on solutions to the above storm-challenged locations with the first two areas in preliminary culvert design stages and the latter, the future Vista Chino Bridge, in the 70% design stage (the City of Palm Springs is the lead agency on this Project). Please slow down and be aware of the roadway conditions during and after this storm.

I will also point out that the Cathedral Canyon Drive crossing at the Whitewater River Channel is not on the above list anymore due to the opening of the Ofelia Bringas Memorial Bridge. With the new Bridge, the Cathedral Canyon Drive crossing at the Whitewater River Channel is no longer a factor when it rains.

Reminder: The Ofelia Bringas Memorial Bridge dedication ceremony, with Congressmembers Raul Ruiz and Michael Levin scheduled to be in attendance, will be on Thursday morning October 6th at 10:00 a.m. on the southeast side of the Bridge. All are invited to come and watch the dedication.

If you have any questions regarding this Community Update, please call John A. Corella, P.E. at 760-770-0327 (JCorella@cathedralcity.gov).

COVID 19 Information

covidbanner21
ccedd-covid1

News

10th Annual Sammy’s International Meatball Festival is Sunday, October 2, 2022

The 10th Annual Sammy’s International Meatball Festival will be held Sunday, Oct. 2, 2022, from noon to 4 p.m. This year the fundraiser will be both virtual and in-person. The in-person festivities will be held at the Boys and Girls Club of Cathedral City club facilities, located at 32-141 Whispering Palms Trail, Cathedral City, CA 92234. The fun filled event … Read more
10th Annual Sammy’s International Meatball Festival is Sunday, October 2, 2022

Photos of the Week

Business Spotlight - Luchador Brewing Company
Luchador Exterior
Luchador Interior
Luchador Vats
68510 E Palm Canyon Dr, Cathedral City
www.luchadorbrew.com (760) 797-2337

Events

Coachella Valley Battle in the Desert

Watch the sport of amateur boxing at the Cathedral City Community Amphitheater in Downtown Cathedral City. Doors open at 6:00 pm 1st boxing match starts at approximately 7:00 pm All ringside tables are SOLD OUT! General admission tickets will be available at the door Saturday, October 1st! COVID-19 restrictions: The State of California recommends that all attendees be fully … Read more
Coachella Valley Battle in the Desert

Tejano Music Festival

Tejano PowerHouse Entertainment, City of Cathedral City and Diaz Enterprises invites you to the rescheduled 4th annual Tejano Music Fest in Cathedral City featuring the best Tejano music, fiesta food and spirits on Saturday, October 29, 2022 from 5 pm to 10 pm at our new location, the Cathedral City Community Amphitheater, 68526 Avenida Lalo Guerrero, in Cathedral City, California. … Read more
TMF22_sq

Halloween Spooktacular

Cathedral City’s Halloween Spooktacular features trick or treating with over 50,000 pieces of candy! Join friends, neighbors, and family for a Spooktacular time including activities such as Halloween costume contests (two bikes given away each hour), police and fire exhibitions, music, and family games. Halloween Spooktacular provides you with information about the police and fire departments, to view special … Read more
Spooktacular2022-logo

Job Openings

AMBULANCE OPERATOR - EMT

  • FULL-TIME EMPLOYEE $15.54 - $20.34 Hourly
  • Department: Fire Department

ANALYST I/II (FINANCE)

  • FULL-TIME EMPLOYEE - $30.00 - $47.74 Hourly
  • Department: Finance

ASSOCIATE/SENIOR CIVIL ENGINEER

  • FULL-TIME EMPLOYEE - $42.22 - $55.26 Hourly
  • Department: ENGINEERING

CROSSING GUARD

  • PART-TIME EMPLOYEE - $15.00 Hourly
  • Department: Police Department

AMBULANCE OPERATOR - PARAMEDIC
(24-hour shifts)

  • FULL-TIME EMPLOYEE - $16.33 - $21.37 Hourly
  • Department: Fire Department
nowhiringsign_1523297863709_83322375_ver1.0_640_480
To view current job opportunities, apply for a position, or submit an interest card, please visit joincathedralcity.org
For Questions or Comments, Contact Ryan Hunt, Communications & Events Manager
rhunt@cathedralcity.gov
facebook twitter youtube linkedin